Warehouse District Street Construction Report


To and From



$25,000,000 in Street Reconstruction is underway.
____________ 

Good morning,
I hope your holiday weekend is off to a great start. 

Things are progressing on the project, and now that a significant amount of the underground work is done, things are taking shape above ground.  Here’s what’s scheduled for next week:

·         On Adams Street, a layer of asphalt will be placed in the parking lanes, as a base for decorative bricks; and decorative bricks will be installed in the sidewalk areas on the riverside of the street.

·         Work on Oak Street between Adams and Jefferson is scheduled to begin Wednesday, September 4th.  Contractor will begin sawing for removal of pavement, curb, sidewalk and driveways, followed by removal later in the week. Two-way traffic will be maintained on Oak Street, with flaggers at times.

Have a great weekend.  As always, if you have any questions or comments regarding the Warehouse District TIGER II Project, please visit our website at http://www.warehousedistrictpeoria.com.  

You can also contact me directly at kdvorsky@terraengineering.com or at (309) 472-3132.

Karen S. Dvorsky, P.E.